ROAD PROJECT - UPDATES

PLEASANT VALLEY ROAD -  should be back on track by next Tuesday, Sept 2nd.  Weather permitting will be completed within 1- 2 weeks.

CHAPEL COURT  -  Reconstruction will begin right after Pleasant Valley and be completed within 1-2 weeks.  Weather permitting, hopefully by end of September.

PARKWOOD COURT  - Reconstruction will also begin right after Pleasant Valley and be mpleted within 1 -2 weeks.  Weather permitting, hopefully by end of September.  

Also during this time-  CULVERTS will be replaced under the road in FAIRHAVEN development.  Also hopefully by end of September.

There is predictions of frost in SE WI the last 2 weeks of September.  OH NO!