Those of you who travel Ulao Parkway South – July 1st – July 22nd Weather permitting Road will be being redone – Please be aware and drive SLOWLY
Here is the expected schedule:
Balance Culverts installed week of July 1
Hauling in millings the week of July 8th grading & reshaping
Paving around the week of July 22nd.